Electronic Board Assembly Tool

Case Study

TURNKEY COMMERCIAL PRODUCTION UPGRADE FROM CONCEPT TO COMPLETION

Facts

  • > 1,700 Hours

  • 2-4 Professionals, 8 Months

  • From discrete and PC controlled to CompactLogix PLC, Wonderware System Platform HMI, Custom SQL Server Recipes and Batch Reports

  • 12 Servo Motors, 1 XY Stage

  • 4 Cognex Vision System Cameras

Services & Deliverables

Successfully engaged Japanese Electronics Manufacturer corporation’s engineering team through all phases of the project development lifecycle.  Delivered an automated system that converted an existing semi-manual assembly tool to fully automated.

Conceptual Engineering Deliverables:
URS, Budget

Preliminary and Detailed Design Deliverables:
Functional Specification (FS), Instrument Datasheets, Software Design Specification + Hardware Design Specification (Single SDD), Control Panel Design.

Construction / Installation Deliverables:
Control Panels, Instrumentation, Control System Software, Factory Acceptance Test (FAT), Site Acceptance Test (SAT), System Startup / Tuning, Production Support.

Want to get in touch?

Use the button below to contact us now.

Contact Us Now

All Case Studies

Green Field

Starting with a blank canvas

Working to help your thoughts and ideas to become a reality.

Site-Wide Upgrades

Align Business & Manufacturing

Migrating legacy production systems to increase reliability, quality, and efficiency.

Production Expansion

Minimizing Shutdown & Construction Duration

Growing existing production capacity to match your supply with market demand.