Chemical Plant Upgrade

Chemical Plant Upgrade

Design-build control system upgrade of fully operational chemical plant

FACTS

• 6 Years, 2-7 Professionals

• On site Electrical/Instrument Trailer

• 900 IO Points

• Allen Bradley PLC

• iFix SCADA and Historian

• 50 Custom SQL Server Reports

• SAP Orders Converted to Recipes for Operators and Equipment via Custom VB Code

• Installation of new Plant Ethernet Network/Thin Client Operator Interfaces

Services & Deliverables

Worked with the Engineering and Production staff of a Japanese headquartered specialty chemical manufacturer to upgrade entire manufacturing plant control system.

Preliminary Engineering and Detailed Design Phase Deliverables:
User Requirement Specification (URS), Functional Specification (FS), Control Panel Design, Plant Network Design

Construction Phase Deliverables:
Control Panel, Instrumentation, Control System Software, Factory Acceptance Test (FAT), Installed 9 Panel Mounted Operator Interface Terminals and Ethernet Network, Site Acceptance Test (SAT), Clean Room and Grey Space Electrical Installation.